The hh2 Unit Production Worksheet is critical to automatically generating a Job/Phase Projection Report on a daily basis.

To access the Unit Production Worksheet, click on “FR” on the left-hand panel, then choose “Unit Production Worksheet. 

The steps to submitting your daily production claims include:

  1. Choose your Job
  2. Filter to your phase, use “XXX-” (for example “125-”) to filter cost codes to just your phase.
  3. Review the Estimated Production Units and Units of Measure.  Generally these quantities are what you can claim, you should not “Overclaim”.
  4. Enter your claimed production units for the day for each available cost code for which work was performed (hours entered in hh2 RP).
  5. Review your weekly subtotal production units.
  6. Review the Job-To-Date total production units.  A grey bar fills in this cell to illustrate percent of production units claimed.  Once all production units are claimed, this cell turns green.  If too many production units are claimed (overclaiming), the cell turns red.
  7. Finalize the daily production unit claims once completed. Automated Reporting WILL NOT be generated unless the Daily Unit Production Claims are finalized.