One advantage of collecting our data electronically through hh2 is the ability to generate automated reporting. Generating weekly Projection Reports for Jobs/Phases was a relatively time consuming task in the past.
Projection Reports will be automatically generated and emailed to stakeholders provided that three things occur daily:
- Time sheet manhours are accurately entered in hh2 RP
- A Daily Log is entered AND Finalized in hh2 FR
- Unit Production data is entered AND Finalized in the hh2 FR - Unit Production Worksheet
An example Projection Report is below. The report has seven primary features:
- Cost Code-Description-Units of Measure (Grey Columns)
- Estimated Production Units and Manhours (Yellow Columns)
- Job-To_Date Production Units, Manhours and Percent Complete (first three Light Blue Columns)
- Total Projected Manhours and Over/Under projection (last two Light Blue Columns)
- Production Units and Manhours claimed for the most recent day
- Totals Row - first row below the Cost Code list, shows Totals and Overall Over/Under for the Job/Phase.
- Travel and Subsistence Summary - Shows Estimated versus Job-To-Date Travel and Per Diem for the Job/Phase.