Phase 125 – Site Development
Standard equipment for Site Development crews is quite simple . . . a Vehicle, sometimes a Trailer and/or Welder/Generator.  Standard quantities are shown in parentheses ().
  • VEHX-XXXX Vehicle (1)
  • WLD-5005 Welder/Generator 150-250 AMP (1)               If Onsite
  • TRL-7010 Trailer Fleet (1)                                           If Onsite

Phase 130 – Pedestal
Standard equipment for Pedestal crews during the Pedestal Build phase include:
  • VEHX-XXXX Vehicle (1)
  • BOX-1010 Pedestal Tool Box (Conex) (1)
  • CRN-21XX Tower Crane (1)
  • CRT-2310 Lattice Towers - Type C, 40‘ (3)
  • SEC-1000 Mobile Security Unit (1)
  • PED1-10XX XX' Ped Build Package – Wood (1) XX = Ped Diameter

Once the Pedestal Build is complete, defined as “The Dome is completed and the Tower Crane is removed from the tower, the Standard Equipment package for crews will change.  The Standard Equipment for Pedestal crews during the Pedestal Stripout phase include:
  • VEHX-XXXX Vehicle (1)
  • BOX-1010 Pedestal Tool Box (Conex) (1)
  • CRT-2310 Lattice Towers - Type C, 40‘ (3)
  • SEC-1000 Mobile Security Unit (1)
  • PED3-30XX XX' Ped Strip Package (1)             XX = Ped Diameter
Phase 140 – Steel Ground
Standard Equipment for Steel-Ground crews include:
  • VEHX-XXXX Vehicle (1)
  • BOX-1020 Steel Tool Box (Conex) (1)
  • GENX-53XX Production Generator (1)
  • WLD-5010 Welder 350-500 AMP & Suitcase (5)
  • SEC-1000 Mobile Security Unit (1)
  • WLD-51XX Cone Suspension System (1)
  • AIR-6210         Elctrcl Air Compressor (Steel) (1)
  • ACC-4020 Steel Ground Access Package (1)
  • WLD-5030 AWG1 (3 O'Clock) (CET-IN USE) (1) Only When In Use

Phase 150/172 – Steel Air
Standard Equipment for Steel-Air crews include:
  • VEHX-XXXX Vehicle (1)
  • BOX-1020 Steel Tool Box (Conex) (1)
  • GENX-53XX Production Generator (1)
  • WLD-5010 Welder 350-500 AMP & Suitcase (5)
  • SEC-1000 Mobile Security Unit (1)
  • ACC-4030 Steel Air Access Package (1)

Phase 155/156 – Coatings
Standard Equipment for Coatings crews include:
  • VEHX-XXXX Vehicle (1)
  • BOX-1030 Coatings Tool Box (Conex) (1)
  • AIR-61XX Air Compressor (1)
  • CTG-6210 Blast Pots- 500 Lb to 2 Ton (2)
  • CTG-6230 Single Leg Paint Pumps (2)
  • ACC-4010 Coatings Access Package (1)
  • TRL-7010 Trailer Fleet (1)
  • CTG-6240 Plural Component Paint Pump (1)      If Onsite
  • CTG-6250 ARS Blaster/Recovery Unit (1)      If Onsite
  • CTG-6260 Ctgs Warranty/Repair Trailer (1)      If Onsite
  • CTG-6270 TEPE Containment System (1)           If Onsite

Phase 160 – Finish Out
Standard equipment for Finish Out crews is quite simple . . . a Vehicle, sometimes a Trailer and/or Welder/Generator.  
  • VEHX-XXXX Vehicle (1)
  • WLD-5005 Welder/Generator 150-250 AMP (1)               If Onsite
  • TRL-7010 Trailer Fleet (1)                                           If Onsite

All Crews

If multiple Vehicles are onsite, they must each be claimed. The Vehicle ID’s stenciled on each vehicle correspond the the last four digits of the Equipment Code. If the crew is utilizing a Vehicle for which the Company is paying a Vehicle Allowance, the Equipment Code VEH4-6000 must be claimed.